State reps review bridge carrying
water line
|

Photo By Rick Harris
State and federal reps meet with city of Elizabethton
officials to review the condition of the decrepit bridge
supporting the Doe River water line.
|
By Thomas Wilson
STAR STAFF
twilson@starhq.com
State and federal representatives spent Tuesday morning examining
a decrepit bridge that structurally maintains a water transmission
line responsible for supplying 33 percent of Elizabethton's
drinking water.
City officials met with representatives from the Tennessee
Valley Authority, U.S. Army Corps of Engineers and Tennessee
Department of Environment and Conservation (TDEC) on Tuesday
afternoon to visit the city's Doe River water transmission
line carrying potable water from the Hampton Spring source.
"It did appear to be impacted," said Andrew Tolley, with TDEC
Division of Water Pollution Control at the Environmental Assistance
Center in Johnson City.
A 16-inch water line encased in concrete extends roughly 240
linear feet across the abandoned U.S. Highway 19E bridge that
crosses the Doe River. At issue is the structural soundness
of the bridge. At stake is the potable water supply to city
of Elizabethton water customers.
"They realized in fact, after going up there that it is an
emergency situation and that something needs to be done as
soon as possible," said David Ornduff, director of planning
and development, who, along with Public Works Director Ted
Leger brought government reps to the bridge.
If the line relocation involves entry into the river, the
city must secure an Aquatic Resource Alteration Permit (ARAP)
from TDEC. The permit application would be forwarded to the
other agencies for review. Tolley said, depending on the size
and scope of the project, an ARAP permit could be issued in
a few days or six months.
In an evaluation of the bridge in June 2002, the engineering
firm of J.R. Wauford & Co. found the bridge had begun
a rapid deterioration, was somewhat unstable "and could possibly
fall" in the immediate future. The firm found a 46-foot portion
of the bridge's western wall and a bridge deck had fallen
into the river. The bridge surface near the western wall has
chipped away and is partially closed off with metal fencing.
The firm found the city could not adequate supply its 10,500
customers with potable water if the water line was disrupted
by the continued decay or collapse of the bridge. Wauford
& Co. is handling the engineering work for the line relocation
including securing the ARAP.
"The permitting process is going forward so that there won't
be any loss of time," said Ornduff.
Ornduff said the primary relocation method being considered
involved boring beneath the river bed and laying the line
underground. A secondary option involved doing an "open cut"
into the river and placing the line in the river bed. A third
plan has the line extended along the first of the so-called
"double bridges" on Highway 19E. Connecting the water line
to the highway would require approximately 150 feet of additional
transmission line construction, Ornduff said.
Tolley said if the city chose to bore beneath the river bed
to relocate the line, an ARAP permit would probably still
be necessary.
"That could create a lot of construction on either side of
the river for that to be done," he said.
The city's 14-inch water line from the Hampton Spring source
was washed away in the flood of 1998. Ornduff said that water
line had been placed in the early 1920s.
The city has submitted an application for a $500,000 loan
from the State Revolving Fund (SRF) loan program. Administered
by TDEC's Division of Community Assistance, the SRF Loan Program
provides low-interest loans to cities, counties, and utility
districts for the planning, design, and construction of water
facilities.
After the 1998 flood washed away the city's existing water
line to the Hampton Spring, the city constructed the line
across the bridge to restore water service to thousands of
customers.