Elk Avenue Bridge to be completed
by late May
By Thomas Wilson
STAR STAFF
twilson@starhq.com
Restoration of the Elk Avenue Bridge is not expected
to be done for at least two more months, according to officials
with the Tennessee Department of Transportation who have a
target completion date of May 31 - less than two weeks away
from the beginning of the Covered Bridge Celebration.
"We are not going to open the bridge unless it
is perfectly safe," said Travis Brickey, community relations
officer with TDOT's Region I office in Knoxville. "I think
we are doing that."
The timetable cuts very close to the 38th Annual
Covered Bridge Celebration scheduled for June 9-13. The Elk
Avenue Bridge has traditionally been a staging area for various
festival events. Restoration of the bridge began shortly after
the festival ended last year and the project was originally
estimated to be complete by November 2003.
Downtown merchants and motorists have decried
the project's duration citing lost business and inconvenience
in accessing U.S. Highway 19E and the Carter County Courthouse.
The bridge was built in 1926 by the Luten Bridge
Co. and was once lit by gas lamps. Brickey said construction
crews had no records of the bridge design or structure to
work from once the restoration began. "We really didn't know
going into it what we were getting into," he said.
Brickey said the contractor was forced to replace
the bridge deck and approximately 300 bridge spindles to reinforce
the structure.
The concrete poured in the deck, arches, abutments
and piers when the bridge was first built is being replaced
with modern concrete. Also, the decorative urn bridge railings
will be restored. Brickey said when contractors were removing
the decayed ornate handrails on the bridge, a portion of the
bridge collapsed. The handrails had to be recast and molded.
The existing modern aluminum streetlights have
been removed from the bridge and the original concrete lampposts
are being restored. The new lights will be powered by electricity.
The bridge's age and structural deficiency initially
had it set for replacement. However, after an outcry to restore
the historical integrity of the bridge instead of erecting
a new concrete flat top, City Council members voted to accept
federal funds to restore the bridge rather than replace it.
The project is being funded with federal funds
through the U.S. Department of Transportation. Total cost
of the restoration project exceeds $1 million and is being
completed with 80 percent federal funds administered through
TDOT plus matching funds from the city.
Flooding in November that raised the Doe River
through the county also set the project back several weeks.
Brickey said balancing the historical aesthetics of a bridge
and maintaining its safety could extend a project's time.
"We are going through the same thing here at
the Gay Street Bridge here in Knoxville," he said. "They found
some structural things that had to be replaced because it
wouldn't be safe otherwise."